Latest New School Construction Update

Looking ahead to the upcoming holiday, the New School construction site will be closed on Saturday, December 31st and also on Monday, January 2nd. Next week (January 2 to January 6), Superstructure and concrete work will continue at 2nd and 3rd floor levels. Sidewalk sheds will continue being erected around the perimeter of the site and we will be opening the one on 14th st. The following week (January 9 to January 13), we will continue superstructure concrete and slabs on 2nd and 3rd floor levels. In the upcoming weekend, January 14th, we plan on installing the new crane on Fifth Avenue.

Similar Posts

  • Imagine a Subway

    Travel back to 1901 and take a look at the 4,5,6 train being built up the east side of Union Square. Remarkable images! You can even see the statue of George Washington at bottom center of the first photo. This was his original location, at the intersection of 4th Ave. and 14th St., before he was moved into the park itself.

  • Latest New School Construction Update

    Next week (May 27 to May 31), material and equipment deliveries and installation work will continue on all floors inside the building. We will be working on the new sidewalks around the building and installing new curbs and will be removing the sidewalk shed along 13th st. Additionally we will be working on the roofs of the building. The site will be closed on Monday, the 27th for the holiday.

    The following week (June 3 to June 7), material and equipment deliveries and installation work will continue on all floors as well as sidewalk work.

    This weekend the site will be open on Saturday, May 25th for interior, roof, and sidewalk activities between the work hours of 7AM and 5PM as permitted by the City.

  • Latest New School Construction Update

    Next week (October 1 to October 5), Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on upper floors will continue. Curtain wall installation on the lower floors will proceed along 5th ave inside the construction site. The crane that is on site will remain for the duration of curtain wall installation and will not affect pedestrian or automotive traffic.

    The following week (October 8 to October 12) Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation will continue on all floors. Curtain wall installation on the lower floors will proceed along 5th ave inside the construction site. The site will be open on Monday the 8th.

    This weekend the site will be open on Saturday, September 29th for superstructure related activities and curtain wall installation between the work hours of 7AM and 5PM as permitted by the City. Con Ed is on site working in the street at 14th Street and 5 Avenue.