Latest New School Construction Update

Next week (June 17 to June 21), material and equipment deliveries and installation work will continue on all floors inside the building. We will be working on the new sidewalks around the building on 13th st. as well as taking the sidewalk shed down on 13th st. Additionally we will be working on the roofs of the building.

The following week (June 24 to June 28), material and equipment deliveries and installation work will continue on all floors as well as sidewalk work.

This weekend the site will be open on Saturday, June 15th for interior, roof, and sidewalk activities between the work hours of 7AM and 5PM as permitted by the City.

Similar Posts

  • NYPD 6th Precinct Community Council Meeting–September 25

    The NYPD 6th Precinct Community Council Meeting will take place in person Wednesday, September 25 at 7:00 PM

    Our Lady of Pompeii’s Fr. Demo Hall – Lower Level at the corner of Bleecker and Carmine Streets

    note: meeting will begin promptly at 7:00 pm 

    Please sign in at the door early if you wish to speak or ask questions of the panel.

    Join the leadership of the 6th Precinct, your neighbors and local businesses for an update on community affairs.  This is also your opportunity to advise Precinct Leadership of chronic or specific crime/safety/quality of life problems you see in our community so their actions are directed with your unique insights. Take this opportunity to listen or to voice your thoughts in an open and informative session.  We encourage you to tell/bring a neighbor and be a part of your Community’s voice.

    As part of the planned 2024 enhancements we return to our regular monthly meeting program with our very important September 25th meeting that will feature a comprehensive panel of our Community’s Elected Officials addressing Crime, Safety and Quality of Life in our community.

    Scheduled Panelists:

    -Brad Hoylman-Sigal – State Senator

    -Brian Kavanagh – State Senator

    -Erik Bottcher – City Council

    -Carolina Rivera – City Council

    -Deborah Glick – NY State Representative

  • Good Heavens…Walmart?

    The latest gossip from The Villager:

    While the fate of two prime-time storefronts on the south side of Union Square has yet to be determined, recent whispers have indicated that more big-box stores could be headed for the space currently occupied by a pair of retail behemoths.

    Electronics retailer Circuit City, which filed for bankruptcy late last year, will shutter its location on 14th St. at Fourth Ave. at the end of next month as part of plan to auction off all its properties and leases nationwide.

    A sales associate at the store said that Walmart was interested in the space, which is owned by developer The Related Companies, although a New York-based spokesperson for Walmart said the big-box chain currently has no announced projects in the city.

    Best Buy, which has a store less than a mile away on W. 23rd St., is another name that has been floated as a future tenant. A company spokesperson said the electronics-and-entertainment retailer does not currently have any plans for the site and could not speculate on potential deals.

    Rumors have also swirled for months over the possible departure of the adjacent Virgin Megastore, where Related — which owns a controlling interest of the Virgin stores — is also the landlord.

    “We’ve made no decision about that property,” Related spokesperson Joanna Rose told Mixed Use, echoing her statements to this paper from last May regarding Virgin’s long-speculated exit. However, Rose did confirm that brokerage Winick Realty Group continues to handle the leasing assignment for the nearly 60,000-square-foot property.

    A spokesperson for the Union Square Partnership did not have any information on who could open in either space, where brokers have pegged asking prices for the marquee addresses at upward of $300 to $350 per square foot.

  • Latest New School Construction Update

    Next week (November 21 to November 25), DOT approved street connections to underground utilities on Fifth Avenue and 13th street will continue. Superstructure work will continue at cellar, 1st, and 2nd floor levels. Sidewalk sheds will continue being erected around the perimeter of the site. The project will be closed on Thanksgiving Day, 11/24, and open for work on 11/25 and 11/26, weather pending. The following week (November 28 to December 2), we will continue superstructure concrete and slabs. Street utility connection work will continue.