  • Latest New School Construction Update

    In response to community concerns about the time in the evening we end our concrete placing, DOB has granted our request to start placing our concrete at 6am, which will allow us to finish this work earlier in the evening. We have 10 more instances like this until we finish our superstructure in early June.

    Therefore next week (April 2 to April 6), Superstructure work will continue at the 9th and 10th floor levels. Wednesday, April 4th, we will have an identical pour with a 6 am start time and similar end time, weather permitting. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    The following week (April 9 to April 13), we will continue superstructure concrete and slabs on the 10th and 11th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    This weekend the site will be open on Saturday, March 31st for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities.

    Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

    In addition to the normal work on the job site, the 14th St. Con Ed Vault utility connection street work will continue per DOT Permit granted for weekends only.

  • Latest New School Construction Update

    Next week (October 21st to October 25th), material and equipment deliveries and installation work will continue on the academic floors inside the building and we anticipate paving on 5th Ave.

    The following week (October 28th to November 1st), material and equipment deliveries and installation work will continue on academic floors.

    This weekend the site will be open on Saturday, October 19th for interior activities between the work hours of 7AM and 5PM as permitted by the City.

  • Latest New School Construction Update

    Next week (September 24 to September 28), Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on the upper floors will continue. Curtain wall installation on the lower floors will proceed along 5th ave inside the construction site. The crane that is on site will remain for the duration of curtain wall installation and will not affect pedestrian or automotive traffic.

    The following week (October 1 to October 5) Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation will continue on all floors.

    This weekend the site will be open on Saturday, September 22nd for superstructure related activities and curtain wall installation between the work hours of 7AM and 5PM as permitted by the City. Con Ed is on site working on the building but is not in any of the streets.