A Sad Farewell to Bowlmor’s Friendly Face

From The New York Times’ Metropolitan Diary:

Greenwich Village’s Bowlmor Lanes on University Place, open since 1938 and one of the longest continuously running bowling alleys on the East Coast, shut its doors on Monday to make way for new condominiums.

Much more than the disappearance of another landmark is the loss of Mark Braunreuther, Bowlmor’s man at the door for the past 16 years: benevolent minder, gentleman greeter, peacekeeper on the rowdy corner between Bar 13 and Bowlmor, an area labeled by one resident as the intersection between “Bucket” and “Blood.” On weekends, residents regularly awaken to police sirens and find violent traces splattered on early-morning sidewalks. Mark was always deep in the fray. His judiciousness was the reason so many revelers went home unharmed.

Mark B. was the mayor of University Place. He knew most of us, and all of our pets, by name. Last summer he tended corn seeds in the tree bed out front. Just seeing those struggling cornstalks made one glad for summer. This coming season, he was planning some tomatoes.

Mark regularly brought my husband and me cake from his favorite Queens bakery. The box always included biscuits for our dog. We reciprocated with Carolina barbecue sauce.

Mark lost everything in Hurricane Sandy — his entire apartment and his car. His bosses replaced the car so he could get in from Far Rockaway. And when our Bowlmor closed for good, they promised a good position at their Chelsea Piers location. Mark was very grateful but he admitted he’d miss our neighborhood.

Mark died suddenly a few weeks before Bowlmor Lanes closed its doors forever.

Rest in peace, brave knight. I, for one, will miss you long after a bowling alley is a distant memory.

Similar Posts

  • Latest New School Construction Update

    Next week (February 18 to February 22), material and equipment deliveries and installation work will continue on all floors inside the building as well as roof work. Additionally we will begin work on the new sidewalks around the building. The sidewalk shed on 14th st. is scheduled to begin dismantling, pending construction progress. The site will be closed on Monday, February 18th, for the holiday.

    The following week (February 25 to March 1), Material and equipment deliveries and installation work will continue on all floors and roofs as well as sidewalk work.

  • Latest New School Construction Update

    Next week (October 8 to October 12), Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on upper floors will continue. Curtain wall installation on the lower floors will proceed along 5th ave inside the construction site. The crane that is on site will remain for the duration of curtain wall installation and will not affect pedestrian or automotive traffic.

    The following week (October 15 to October 19) Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation will continue on all upper floors. Curtain wall installation on the lower floors will proceed along 5th ave inside the construction site. The site will be open on Monday the 8th.

    This weekend the site will be open on Saturday, October 6th for superstructure related activities and curtain wall installation between the work hours of 7AM and 5PM as permitted by the City. Con Ed will be working in the street.

  • Ben Ness Gone

    Sad to see local photo store Ben Ness go. It was a good place to get passport phots done and was staffed with a nice bunch of guys. It will be interesting to see if the space goes to a local business or to a chain. Pinkberry perhaps?

  • Latest New School Construction Update

    DOB has granted our request to start placing our concrete at 6am, which will allow us to finish this work earlier in the evening. We have 3 more instances like this until we finish our superstructure in early June.

    Therefore, next week (April 30 to May 4), Superstructure work will continue at the 15th and 16th floor levels. Tuesday, May 1st and Friday, May 4th we will have a pour with a 6 am start time and similar end time, weather permitting. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    The following week (May 7 to May 11), we will continue superstructure concrete and slabs on the 17th floor and roof levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    This weekend the site will be closed.