Bolwmor Demolition: When?
Although Bowlmor Lanes is now officially closed, there have been no demolition permits filed with the DOB. That means it’s unclear when the loud and messy work will begin.
Another name change for the restaurant on the 13th St. side. First it was Izu. Then it was Lemongrass at Izu. Then it was Shanghai Square. Now it’s Dragonfly. To which we say, whatever.
Here’s the official word on how the renovations are going:
Spring weather has brought with it a flurry of activity in Union Square Park, both in the new playground and at the construction site. Parents and kids have been taking full advantage of the warm sunny days by swinging, climbing and sliding their way out of the winter doldrums. The Partnership’s new landscape efforts, including more than 260 ornamental shrubs and 650 perennials, will soon be underway, as well as the creation of additional seating opportunities in the center lawn, in front of the new Pavilion entrance and around the James Fountain (a/k/a Mother & Child).
In construction news, structural work on the Pavilion columns and ceiling beams has finished at last, and the protective plywood barriers have been removed from the front of the building, exposing the beautifully restored neo-classical interior to passersby. As the Pavilion elevator is installed and tested, interior lighting fixtures, gates and handrails round out the final touches of building restoration work.
Park visitors can soon make use of the restroom facilities as they, too, near completion. Last week, eco-resin panels were mounted above the granite walls to enclose the building, allowing the final plumbing fixtures to be installed. Once complete, the Parks Department will work closely with the Department of Buildings to inspect all systems in order to open the facilities for the busy summer season.
After decades on Union Square, Rothman’s men’s clothes is moving up Park Ave South one block to a bigger location. Here are the details.
Next week (May 13 to May 17), material and equipment deliveries and installation work will continue on all floors inside the building. We will be working on the new sidewalks around the building and installing new curbs. Additionally we will be working on the roofs of the building.
The following week (May 20 to May 24), material and equipment deliveries and installation work will continue on all floors as well as sidewalk work.
This weekend the site will be open on Saturday, May 11th for interior, roof, and sidewalk activities between the work hours of 7AM and 5PM as permitted by the City.
Sad to see that Patisserie Fouet on 13th St. is no more. It closed suddenly and without much explanation. Perhaps an end-of-year lease situation. They do have another location at 776 9th Ave at 52nd St.
See your mail or e-mail to get the Zoom log in information for this year’s annual shareholder’s meeting on Wednesday, October 12 at 7 PM.