  • Latest New School Construction Update

    Next week (September 26 to September 30), contractors will continue to excavate earth and rock, loading out material. Line drilling will continue as well in limited areas. Concrete foundation walls at the South East corner of the site and slab on grade work will continue. Interior core foundation work and underground electrical and plumbing will continue. Removal of the interior earth ramp will be completed. DOT approved street connections to underground utilities on Fifth Avenue will progress. The cherry picker crane on site will be removed upon installation of the Superstructure Contractors Crane which will be stationed inside the Fifth Avenue fence.

    The following week (October 3 to October 7 ), we will continue with concrete foundation walls and slabs, line drilling, rock excavation, loading out, interior core foundation work, street utility connections and underground electrical and plumbing. Formwork for superstructure concrete construction will proceed.

    DEP has completed the water main repair along 13th Street. As part of this work the DEP will be completing related road repairs.

    This weekend in addition to the site being open on Saturday, September 24th for foundation related activities between the work hours of 9AM and 5PM as permitted by the City, there will also be a crane installation crew assembling a crawler crane for use by the concrete superstructure contractor.

    Crane installation will involve a partial street closure on Fifth Avenue between E. 14th and E. 13th Streets, as well as a full closure of E. 13th Street between University Place and Fifth Ave. As permitted by the City this activity is to occur between the hours of 6 AM & 9 PM with Sunday, 9/25/11 as a backup date. We don’t plan on needing Sunday for the crane installation unless the weather effects us on Saturday or something else that’s unpredictable prevents the completion of assembly on Saturday. It is anticipated that this work should be completed by end of work day but it could extend until the time allowed.

  • Latest New School Construction Update

    Next week (January 7 to January 11),interior building material and equipment deliveries and installation work will continue on all floors inside the building as well as roof work.

    The following week (January 14 to January 18),interior building material and equipment deliveries and installation work will continue on all floor as well as roof work.

    This weekend the site will be open on Saturday, January 5th for interior and superstructure related activities between the work hours of 7AM and 5PM as permitted by the City.

  • 30-Story Condo to Rise at 5 West 13th St.?

    Prolific New York condo developer Victor Sigoura’s Legion Investment Group got busy this week with a new project on a site it just acquired near Union Square.

    Legion and real estate investment firm EJS Group bought the vacant six-story office building at 5 West 13th Street/8 West 14th Street for $57.5 million, according to property records made public Tuesday. The ink barely had time to dry before Sigoura’s firm filed permits on Friday to tear down the 130,000-square-foot building. The developer likely has plans for more of what it does best: a condo building up to 30 stories tall, according to Crain’s New York Business.