You may remember The Adore on the 13th St. block. Now, a couple of doors down at the former site of the copy shop and, briefly, Blossom de Jour, will be a new French/Japanese bakery called Patisserie Fouet.
Next week (July 22 to July 26), material and equipment deliveries and installation work will continue on all floors inside the building. Asphalt work on 14th st will begin this week to tie in the finished sidewalk. We will be opening the new sidewalk on 13th st. Additionally we will be working on the roofs of the building. Furniture deliveries will take place in the afternoon along 5th ave.
The following week (July 29 to August 2), material, equipment and furniture deliveries and installation work will continue on all floors as well as sidewalk work.
This weekend the site will be open on Saturday, July 20th for interior, roof, and sidewalk activities between the work hours of 7AM and 5PM as permitted by the City.
Closed at the corner of 13th and 6th. Probably because for take out, the food was too pricey. Wonder what will fill that cursed space next.
The New School says:
Next week (August 29 to September 2), Contractors will continue to excavate earth and rock, and load out material. Installation of bracing rakers and line drilling will progress as well. Concrete foundation walls will continue along the perimeter of the site. Interior core foundation work and underground electrical and plumbing will proceed. Contractors will be removing the interior earth ramp. A small cherry picker crane will be delivered to the site next week and will be stationed inside the Construction fence. This crane will remain there for approximately two months.
The following week (September 6 to September 9 ), we will continue with concrete foundation walls, line drilling, rock excavation, loading out, interior core foundation work, and underground electrical and plumbing. Concrete pours for the slab on grade are anticipated to start this week. The site will be closed for Labor Day weekend (Saturday, Sept. 3 through Monday, Sept. 5).
DEP will continue to repair the water main along 13th Street. As part of this work, the DEP may periodically shut water service off. This work is out of our control.
The NYPD 6th Precinct Community Council Meeting
will take place in-person
Wednesday, November 20 at 7:00 PM
Our Lady of Pompeii’s Fr. Demo Hall – Lower Level
at the corner of Bleecker and Carmine Streets
Guest Speaker: Jessica Mates, Deputy Director
NYS Attorney General Leticia James’ Office
Join the leadership of the 6th Precinct, your neighbors and local businesses for an update on community affairs. This is also your opportunity to advise Precinct Leadership of chronic or specific crime/safety/quality of life problems you see in our community so their actions are directed with your unique insights. Take this opportunity to listen or to voice your thoughts in an open and informative session. We encourage you to tell/bring a neighbor and be a part of your Community’s voice.
All meetings starts promptly at 7:00 PM
Please arrive early to sign in and register as a speaker.
Some folks requested to submit questions before the meeting. Please feel free to send them to 6thpctcommunitycouncil@gmail.com they will be addressed in the meeting.