Summer in the Square Events Listing

Click here to find out all about the many events in the Summer in the Square series that will take place in Union Square over the next few months. There is lots to do.

Similar Posts

  • Latest New School Construction Update

    Next week, 03/04/2013 – 03/08/2013 Material and equipment deliveries and installation work will continue on all floors inside the building. Roof work, work on the new sidewalks around the building, and the dismantling of the construction hoist on the building exterior will also continue.

    The following week, 03/11/2013 – 03/15/2013 Material and equipment deliveries and installation work will continue on all floors and roofs. Sidewalk work and dismantling of the construction hoist on the building exterior will also continue.

    We anticipate the take down of the 14th Street sidewalk shed to begin within the next 2 weeks.

  • Latest Construction Update: More of the Same

    From The New School:

    Next week (September 19 to September 23), Contractors will continue to excavate earth and rock, and load out material. Installation of bracing rakers and line drilling will progress as well. Concrete foundation walls around the perimeter of the site and slab on grade work will continue. Interior core foundation work and underground electrical and plumbing will proceed. Contractors will be removing the interior earth ramp. DOT approved street connections to underground utilities on Fifth Avenue will progress. A small cherry picker crane will arrive on site next week, and be stationed inside the Fifth Avenue fence. This crane will remain on site for approximately two months.

    The following week (September 26 to September 30 ), we will continue with concrete foundation walls and slabs, line drilling, rock excavation, loading out, interior core foundation work, street utility connections on Fifth Avenue, and underground electrical and plumbing.

    DEP continues to repair the water main along 13th Street. As part of this work, the DEP may periodically shut water service off. This work is out of our control.

    The site will be open on Saturday, September 17th. Work hours are between 9AM and 5PM as permitted by the City. To control noise levels, work activities will be limited to the placement of formwork, plumbing and electrical work, site utility connections, waterproofing and rebar for concrete placement, and the installation of walers and braces. There will be no rock excavation, rock chopping, or hauling on Saturday.