    Next week (October 14th to October 18th), material and equipment deliveries and installation work will continue on the academic floors inside the building.

    The following week (October 21st to October 25th), material and equipment deliveries and installation work will continue on academic floors.

    This weekend the site will be open on Saturday, October 12th for interior activities between the work hours of 7AM and 5PM as permitted by the City.

  • New 14th St. Tech Hub Will Include a Food Hall

     

    from 6sqft:

    Pioneering food hall operator Urbanspace is opening its latest outpost at Union Square reports the NY Post. They’ve leased 10,000 square feet at Zero Irving, the contested tech hub on 14th Street that will serve as office space, a technology training center and incubator, co-working spaces, and an event space when it opens in the first half of 2021.

    Located at 124 East 14th Street, at the former site of the P.C. Richard & Son building, Zero Irving has faced opposition for years, as local preservationists and community groups felt that the rezoning required for the development should have included protections for the surrounding neighborhood, which is largely low-rise and residential.

    Nevertheless, the $200 million project has been under construction for the past year. Despite the thousands of small business closings around the city, UrbanSpace founder and president Eldon Scott is confident in what will be his company’s fifth food hall in New York City. “We have the ideal business model to help the New York culinary world recover,” he told the Post.

    UrbanSpace’s other locations are Urbanspace Vanderbilt near Grand Central (the first location, which opened in 2015), Lexington Avenue and 51st Street, 135 West 50th Street, and 152 West 52nd Street. They’re also behind the holiday markets in Grand Central, Union Square, Columbus Circle, and Bryant Park, as well as seasonal food market pop-ups like those at Madison Square and the Garment District.

  • Latest New School Update

    Next week (October 31 to November 4), Contractors will finish excavating and loading out material. Concrete foundation walls and slab on grade work will conclude as well as underground electrical and plumbing work. DOT approved street connections to underground utilities on Fifth Avenue will progress. Superstructure work will continue at cellar, 1st, and 2nd floor levels.

    The following week (November 7 to November 11), we will continue superstructure concrete and slabs. Street utility connection work will continue. A sidewalk shed will be erected around the perimeter of the site, subject to DOB approval, to protect pedestrians from superstructure work.

    This weekend the site will be open on Saturday, October 29 for foundation and superstructure related activities between the work hours of 9AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork, plumbing and electrical work, waterproofing and rebar for concrete placement and use of the crane and equipment to support all activities. We may pour a section of slab on grade concrete on Saturday. There will be no rock excavation or rock chopping.