    Laura Maniec, one of only eighteen female master sommeliers in the world and, at 31, currently the youngest, is about to open her own studio and wine bar. Maniec, who served as wine director at BR Guest for ten years and has just launched the wine program at Niko, has signed a lease on a space at 13 East 13th Street in Union Square and plans to unveil Corkbuzz in May. “It will be an extension of your living room and a place for all things wine,” she tells us. In addition to serving vintages from all over the world, Corkbuzz will offer small plates from oysters and sea urchin to pastas and cheese. The 2,500-square-foot space will also host classes, tastings, and events.

  • Latest New School Construction Update

    Next week (July 9 to July 13), Mechanical equipment and work will continue at the 17th and 18th floor levels. Curtain wall will continue to be installed on the building. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    The following week (July 16 to July 20), we will be working on the machine room levels on the 17th and 18th floors. Curtain wall will continue to be installed on the building. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    This weekend the site will be open on Saturday, July 7th for superstructure activities as well as the demobilization of the crane from the site. In order to facilitate this effort we will be closing 13th street for the day to pedestrian and automotive traffic. Site work will begin at 6AM as permitted by the City. To control noise levels within the site, work activities will be limited to working on the mechanical systems of the building and using the crane and equipment to support activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

  • Latest New School Construction Update

    Next week, 03/18/2013 – 03/22/2013 mMaterial and equipment deliveries and installation work will continue on all floors inside the building. Roof work, work on the new sidewalks around the building, dismantling of the exterior construction hoist and related exterior building work will also continue. Take-down of the 14th Street sidewalk shed will begin this week and will be followed by continued site work on 14th Street.

    The following week, 03/25/2013 – 03/29/2013 material and equipment deliveries and installation work will continue on all floors and roofs. Sidewalk work and dismantling of the exterior construction hoist and related exterior work will also continue. Site work on 14th Street will continue.

    The site will be open this weekend for continued hoist removal related activities between the work hours of 7AM and 5PM as permitted by the City.

  • Latest New School Construction Update

    Next week (February 20 to February 24), Superstructure work will continue at 5th and 6th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    The following week (February 27 to March 2), we will continue superstructure concrete and slabs on the 5th and 6th floor levels. Deliveries will continue to arrive at the site. The site will not be open on Monday the 20th, Presidents’ Day holiday.

    This weekend the site will be open on Saturday, February 18th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.