Shorter Pride Parade Means Bigger Crowds

Due to city budget cuts, this year’s gay pride parade will be a mile shorter than in previous years. That means the usual big crowds along 5th Ave in the Village are going to be even that much bigger. Brace yourself.

Similar Posts

  • Take the Union Square Partnership Opinion Survey

    The USP says: “We want to hear from you! Our 2025 Community Opinion Survey is now live. Share your feedback, ideas, and opinions to help shape the future of the Union Square-14th Street District. Your responses help us understand the community’s priorities and how we can better serve you. The survey closes 5:00 PM on Thursday, September 18th, 2025 — take it today!”

     

    Here’s the link.

  • Entertainment in the Park

    The 2011 “Summer in the Square,” at Union Square, provides early morning fitness, family fun for kids and parents, and live music every Thursday until Aug. 11.  In the evening, live music is presented, beginning at 6 p.m., from a diverse mix of genres like latin, rock, jazz, and folk and a mix of local and touring bands. The exception was June 30, when three groups performed. One of them, “Million Dollar Quartet,” is based on the grand recording session where legends Elvis Presley, Johnny Cash, Carl Perkins, and Jerry Lee Lewis were brought together.

  • Latest New School Construction Update

    Next week (May 20 to May 24), material and equipment deliveries and installation work will continue on all floors inside the building. We will be working on the new sidewalks around the building and installing new curbs and will be removing the sidewalk shed along 13th st. Additionally we will be working on the roofs of the building.

    The following week (May 27 to May 31), material and equipment deliveries and installation work will continue on all floors as well as sidewalk work.

    This weekend the site will be open on Saturday, May 18th for interior, roof, and sidewalk activities between the work hours of 7AM and 5PM as permitted by the City.

  • Latest New School Construction Update

    I write to remind all that the lower 8 floors of this building are still a construction site which is regulated by the Department of Buildings. New School has heard your complaints but at this time we do not control this site. It is our hope that when we take over the building we can make some necessary changes. The University Center is a LEED building with many energy saving designs incorporated into the building so that we will be good neighbors.

    Next week (December 23rd to December 27th ), material and equipment deliveries and installation work will continue on the academic floors inside the building. (Site closed on Christmas)

    The following week (December 30th to January 3rd ), material and equipment deliveries and installation work will continue on academic floors (Site closed on New Year’s Day)

    This weekend the site will be open on Saturday and Sunday, December 21st and 22nd for interior activities between the work hours of 7AM and 7PM as permitted by the City.

  • The Latest on Park Construction

    From the park association: It’s crunch time in Union Square Park as the North End Project reaches 83 percent and enters into the final stretch. New granite curb has been installed along Union Square East, and crews are hard at work paving the east side and 16th Street transverse. Next, they will install the playground’s south perimeter fence once paving is complete. To recap, at this time the landscaping is finished and the park’s new trees, shrubbery and perennials are taking root. Most of the plazas having been reopened to the public and the Greenmarket is fully operational on site in time for their busy fall season. Pavilion restoration continues, though hampered by graffiti removal that has proven challenging, and the new restroom facility on the east side of the project area is nearing completion.

  • Latest New School Construction Update

    Next week (March 19 to March 23), Superstructure work will continue at the 8th floor level. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    The following week (March 26 to March 30), we will continue superstructure concrete and slabs on the 8th and 9th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    This weekend the site will be open on Saturday, March 17th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

    In addition, tomorrow, Friday the 16th, we will be starting operations at 6am in anticipation of a large concrete pour and will more than likely, with notification of the Department of Buildings, be going later into the evening to finish. Also on the weekend of the 10th the 14th St. Con Ed Vault utility connection street work will continue per DOT Permit granted for weekends only.