Duane Reade, Big One, Open
The city’s biggest Duane Reade has opened on 14th St. next to Best Buy and Nordstrom Rack. It’s open 24 hours, as is Best Buy. Shop all night.
Japonica will leave its location as Bowlmor Lanes preps for demolition. It will move just one block south to 90 University Place.
Next week (April 9 to April 13), Superstructure work will continue at the 12th and 13th floor levels. Wednesday, April 4th, we will have an identical pour with a 6 am start time and similar end time, weather permitting. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.
The following week (April 16 to April 20), we will continue superstructure concrete and slabs on the 1th and 14th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.
This weekend the site will be CLOSED on Saturday, April 7th.
Next week (October 29 to November 2), Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on the lower floors will proceed along 14th st. inside the construction site. The crane that is on site will remain for the duration of curtain wall installation and will not affect pedestrian or automotive traffic.
The following week (November 5 to November 9) Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on the lower floors will proceed along 14th st. inside the construction site.
This weekend the site will be open on Saturday, October 27th for superstructure related activities and curtain wall installation between the work hours of 7AM and 5PM as permitted by the City. Con Ed will be working in the street.
Next week (July 9 to July 13), Mechanical equipment and work will continue at the 17th and 18th floor levels. Curtain wall will continue to be installed on the building. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.
The following week (July 16 to July 20), we will be working on the machine room levels on the 17th and 18th floors. Curtain wall will continue to be installed on the building. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.
This weekend the site will be open on Saturday, July 7th for superstructure activities as well as the demobilization of the crane from the site. In order to facilitate this effort we will be closing 13th street for the day to pedestrian and automotive traffic. Site work will begin at 6AM as permitted by the City. To control noise levels within the site, work activities will be limited to working on the mechanical systems of the building and using the crane and equipment to support activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.