New Hotel Will Rise on 13th St.

Mid block between 5th and 6th Aves. will be the local of a new 133-room hotel. It’ll be interesting to see how they squeeze it in. Here are the details.

Similar Posts

  • Momofuku Milk Bar Branch Opens Nearby

    Nostalgic dessert chain Milk Bar is opening its 10th New York City location Saturday, but this time with new menu items only available at this store near Union Square.

    Located at 110 Fifth Ave. and 16th Street, this latest Milk Bar is a part of a new store called Camp, created to be “immersive” shopping for families. The 10,000-square-foot space has a camp theme that will change every eight to 12 weeks, with “base camp,” modeled after children’s summer camps, first up.

    To fit into the camp theme, Milk Bar will have a sundae bar with a rotating special — starting off, appropriately, with a s’mores sundae of cereal milk soft serve topped with compost cookie crumbs, charred marshmallows, fudge sauce, and marshmallow sauce. The sundae bar also has very Milk Bar-esque topping options such has cornflake crunch, confetti cookie crumb, and blueberry corn. And Milk Bar classics — crack pie, corn cookie, birthday cake truffles — fill out the rest of the menu, in full below. There’s also Counter Culture coffee.

  • Latest New School Construction Update

    Next week (September 26 to September 30), contractors will continue to excavate earth and rock, loading out material. Line drilling will continue as well in limited areas. Concrete foundation walls at the South East corner of the site and slab on grade work will continue. Interior core foundation work and underground electrical and plumbing will continue. Removal of the interior earth ramp will be completed. DOT approved street connections to underground utilities on Fifth Avenue will progress. The cherry picker crane on site will be removed upon installation of the Superstructure Contractors Crane which will be stationed inside the Fifth Avenue fence.

    The following week (October 3 to October 7 ), we will continue with concrete foundation walls and slabs, line drilling, rock excavation, loading out, interior core foundation work, street utility connections and underground electrical and plumbing. Formwork for superstructure concrete construction will proceed.

    DEP has completed the water main repair along 13th Street. As part of this work the DEP will be completing related road repairs.

    This weekend in addition to the site being open on Saturday, September 24th for foundation related activities between the work hours of 9AM and 5PM as permitted by the City, there will also be a crane installation crew assembling a crawler crane for use by the concrete superstructure contractor.

    Crane installation will involve a partial street closure on Fifth Avenue between E. 14th and E. 13th Streets, as well as a full closure of E. 13th Street between University Place and Fifth Ave. As permitted by the City this activity is to occur between the hours of 6 AM & 9 PM with Sunday, 9/25/11 as a backup date. We don’t plan on needing Sunday for the crane installation unless the weather effects us on Saturday or something else that’s unpredictable prevents the completion of assembly on Saturday. It is anticipated that this work should be completed by end of work day but it could extend until the time allowed.