Looking for a Super Super
The board is currently searching for a super. It is taking a bit of time, but obviously it wants to make the right decision and find the perfect person. Please stand by.
Our newest neighborhood business, Crumbs Cupcakes, opens on Friday on University between 13th and 14th. The big news: they’ll give away 1,000 cupcakes. No word yet on the opening time, but line up early.
From the Observer:
Jason Scherr, owner of the cafe that the New York Press named best new coffee shop in 2008, has signed a lease for about 1,600 square feet at 123 Fourth Avenue, between 12th and 13th streets, in which he will open his third Think Coffee by the end of the summer, according to Jason Turner, his broker at Zelnik & Company Real Estate. Think is taking the space of the closed Panorama Galleries on an otherwise rather shoddy block that just happens to be steps away from N.Y.U.’s Third Avenue North dorms and its soon-to-be-completed new dorm on 12th Street.
Think Coffee’s two other cafes are at One Bleecker Street and 248 Mercer Street.
“Think Coffee thought it was an emerging street that had some upside,” Mr. Turner said. “Rents are significantly lower than on Broadway or University, so he can be within the Union Square submarket without having to pay Union Square rents.”
DOB has granted our request to start placing our concrete at 6am, which will allow us to finish this work earlier in the evening. We have 3 more instances like this until we finish our superstructure in early June. Friday, May 4 we will have a pour at the 16th floor with a 6am start time and similar end dime, weather permitting.
Therefore, next week (May 7 to May 11), Superstructure work will continue at the 17th floor level. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.
The following week (May 14 to May 18), we will continue superstructure concrete and slabs on the 17th floor and roof levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.
This weekend the site will be open on Saturday, May 5th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise. In addition to the normal work on the job site, we will have an additional crane on site at 5th ave. to install the stair trusses on the west side of the building. The crane will be completely on site and should not interfere with pedestrian or automotive traffic in the area.