Latest Construction Update from The New School

Next week (August 22 to August 26), contractors will continue to excavate earth and rock, and load out material. Installation of bracing rakers, line drilling, lagging and sheeting around the perimeter will progress as well. Concrete foundation walls will continue along the perimeter of the site. Interior core foundation work will continue along the perimeter of the site. Interior core foundation work will proceed. The following week (August 29 to September 3 ), we will continue with concrete foundation walls, line drilling, rock excavation, loading out, and interior core foundation work & underground plumbing. DEP will continue to work on the water main along 13th Street.