Latest New School Construction Update

Next week (October 10 to October 14), contractors will continue to excavate earth and load out material. Concrete foundation walls at the South East corner of the site and slab on grade work will continue. Underground electrical and plumbing work will continue. DOT approved street connections to underground utilities on Fifth Avenue will progress. Formwork and rebar for superstructure will continue at cellar levels.

The following week (October 17 to October 21 ), we will continue superstructure concrete and slabs, street utility connections and underground electrical and plumbing.

Similar Posts

  • Latest New School Construction Update

    Next week (January 28 to February 1), material and equipment deliveries and installation work will continue on all floors inside the building as well as roof work. Additionally we will begin work on the new sidewalks around the building.

    The following week (February 4 to February 8), Material and equipment deliveries and installation work will continue on all floors and roofs as well as sidewalk work.

    This weekend the site will be open on Saturday, January 26th for interior, superstructure and sidewalk related activities between the work hours of 7AM and 5PM as permitted by the City.

  • Here’s the New Megacondo on University

    From Curbed.com:

    Word of the imminent demise of Greenwich Village’s iconic Bowlmor Lanes arrived in early 2014, when EV Grieve reported that site owner Billy Macklowe—whose father is none other than Harry Macklowe of 432 Park Avenue fame—wanted to slap a condo tower up on the site. Details of the new development have been few and far between in the meantime, but 6sqft has gleaned a few primary renderings of the project that seem to confirm 1) that it’s actually happening, and 2) that it will be amongst the tallest residential buildings in the neighborhood. According to 6sqft, the building will rise 23 stories to stand a “modest” 280 feet, and will contain 56 condos averaging more than 2,000 square feet apiece.

    Plans filed with the Department of Buildings list SLCE as the Architect of Record, but a design architect has yet to be pegged, at least publicly, for the project. The building, which consumes a majority of the western side of the block between East 12th and East 13th streets, will have bike parking, a ground-floor community facility, a resident lounge and terrace, a parking garage, and ground floor retail.

    RIP RIP2

  • Latest New School Construction Update

    In response to community concerns about the time in the evening we end our concrete placing, DOB has granted our request to start placing our concrete at 6am, which will allow us to finish this work earlier in the evening. We have 8 more instances like this until we finish our superstructure in early June.

    Therefore next week (April 16 to April 20), Superstructure work will continue at the 13th and 14th floor levels. Wednesday, April 18th, we will have an identical pour with a 6 am start time and similar end time, weather permitting. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    The following week (April 23 to April 27), we will continue superstructure concrete and slabs on the 15th and 16th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    This weekend the site will be open on Saturday, April 14st for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

    In addition to the normal work on the job site, the 14th St. Con Ed Vault utility connection street work will continue per DOT Permit granted for weekends only.