Latest New School Construction Update

Next week (December 12 to December 16), DOT approved street connections to underground utilities on Fifth Avenue have been completed. Superstructure work will continue at 1st and 2nd floor levels. Sidewalk sheds will continue being erected around the perimeter of the site. The roof protection at USC Condo courtyard will be started this week as well.

The following week (December 19 to December 23), we will continue superstructure concrete and slabs on 1st and 2nd floor levels.

This weekend the site will be open on Saturday, December 3rd for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork, plumbing and electrical work, rebar for concrete placement and use of the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

Similar Posts

  • Latest New School Construction Update

    Next week (February 20 to February 24), Superstructure work will continue at 5th and 6th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    The following week (February 27 to March 2), we will continue superstructure concrete and slabs on the 5th and 6th floor levels. Deliveries will continue to arrive at the site. The site will not be open on Monday the 20th, Presidents’ Day holiday.

    This weekend the site will be open on Saturday, February 18th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

  • Wall Street Journal Analyzes Booming University Place

    The Wall Street Journal has a lot to say about what’s happening in our neighborhood. For example: ““I think the area was quite spectacular and bohemian to begin with, but it’s becoming a bit more adult,” said Madeline Hult Elghanayan, a broker at Douglas Elliman Real Estate. “You now see a new, luxury-oriented clientele that’s looking for places to live in this immediate area.“

     

    NY-DK529_NYBLOC_16U_20150122181511

  • Latest New School Construction Update

    Next week (March 5 to March 9), Superstructure work will continue at 6th and 7th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    The following week (March 12 to March 16), we will continue superstructure concrete and slabs on the 7th floor level.

    This weekend the site will be open on Saturday, March 3rd for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

    In addition to the normal work we will be having the boilers delivered to the site on Saturday along the 5th Ave. entrance to the site. The 14th St. Con Ed Vault utility connection street work will continue per DOT Permit granted for weekends only.