Latest New School Construction Update

Next week (February 6 to February 10), Superstructure work will continue at and 4th and 5th floor levels. The following week (February 13 to February 17), we will continue superstructure concrete and slabs on 4th, 5th and 6th floor levels.

This weekend the site will be open on Saturday, February 4th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

14th Street Con ED vault utility connection street work will continue per DOT Permit granted for weekends only.