Latest New School Construction Update

Next week (July 23 to July 27), Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on upper floors will continue and lower levels will begin on 13th st. with the aid of a small crane. We have relocated the 5th ave. sidewalk shed/pedestrian walkway to the exterior of the building.

The following week (July 30 to August 3) Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation will continue on all floors.

This weekend the site will be open on Saturday, July 21st for superstructure related activities and curtain wall installation between the work hours of 7AM and 5PM as permitted by the City.