Latest New School Construction Update

Next week (July 16 to July 20), Mechanical equipment deliveries and work on them will continue at the 17th and 18th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue. Curtain wall installation will continue.

The following week (July 23 to July 27), we will be working on the machine room levels on the 17th and 18th floors. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

This weekend the site will be open on Saturday, July 14th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

Similar Posts

  • Tammany Hall To Undergo Big Changes

    A major renovation is coming to the former Tammany Hall headquarters in Union Square where owners want to put a new glass dome over the landmarked building and demolish a theater to make way for retail and office space, the project’s architects said.

    The historic structure at 44 Union Square East, built in 1929 to house the Democratic Party machine, will undergo a major overhaul that will restore the facade, gut the existing theater and add windows and glassier storefronts, according to BKSK Architects which is designing the project.

    The most striking change will be a new 30-foot glass dome on top of the building, which will add about 27,000 square feet to the structure and will house office space, according to Harry Kendall, a partner at BKSK.

    “Our effort is…to make it a more distinctive destination and presence on Union Square,” Kendall said. “We think we can make this building into something it never was.”

    After hearing a presentation about the proposal this week, Community Board 5’s Landmarks Committee voted unanimously to reject it, saying the changes would be too drastic for an historic building that was just landmarked last year.

    “While I like the way it looks — can you put something like this on a landmarked building?” said Edward Klimerman, a committee member. “It turns it into a different building.”

    The Landmarks Preservation Commission designated the building as a landmark in June 2013, noting its references to early American architecture, including Colonial columns out front. The building’s design drew inspiration from the original Federal Hall in Lower Manhattan, where George Washington took his first oath of office.

  • Latest Construction Update: More of the Same

    From The New School:

    Next week (September 19 to September 23), Contractors will continue to excavate earth and rock, and load out material. Installation of bracing rakers and line drilling will progress as well. Concrete foundation walls around the perimeter of the site and slab on grade work will continue. Interior core foundation work and underground electrical and plumbing will proceed. Contractors will be removing the interior earth ramp. DOT approved street connections to underground utilities on Fifth Avenue will progress. A small cherry picker crane will arrive on site next week, and be stationed inside the Fifth Avenue fence. This crane will remain on site for approximately two months.

    The following week (September 26 to September 30 ), we will continue with concrete foundation walls and slabs, line drilling, rock excavation, loading out, interior core foundation work, street utility connections on Fifth Avenue, and underground electrical and plumbing.

    DEP continues to repair the water main along 13th Street. As part of this work, the DEP may periodically shut water service off. This work is out of our control.

    The site will be open on Saturday, September 17th. Work hours are between 9AM and 5PM as permitted by the City. To control noise levels, work activities will be limited to the placement of formwork, plumbing and electrical work, site utility connections, waterproofing and rebar for concrete placement, and the installation of walers and braces. There will be no rock excavation, rock chopping, or hauling on Saturday.

  • Latest New School Construction Update

    Next week (December 24 to December 28), material and equipment deliveries and installation work will continue on all floors inside the building. The site will be closed on December 25th for the holiday but will be open on Monday the 24th and Wednesday the 26th.

    The following week (December 31 to January 4), Material and equipment deliveries and installation work will continue on all floors.

    This weekend the site will be open on Saturday, December 22nd for interior and superstructure related activities between the work hours of 7AM and 5PM as permitted by the City.