Latest New School Construction Update

Next week, 03/18/2013 – 03/22/2013 mMaterial and equipment deliveries and installation work will continue on all floors inside the building. Roof work, work on the new sidewalks around the building, dismantling of the exterior construction hoist and related exterior building work will also continue. Take-down of the 14th Street sidewalk shed will begin this week and will be followed by continued site work on 14th Street.

The following week, 03/25/2013 – 03/29/2013 material and equipment deliveries and installation work will continue on all floors and roofs. Sidewalk work and dismantling of the exterior construction hoist and related exterior work will also continue. Site work on 14th Street will continue.

The site will be open this weekend for continued hoist removal related activities between the work hours of 7AM and 5PM as permitted by the City.