Luxoft is a leading provider of software development services and innovative IT solutions to a global client base consisting primarily of large multinational corporations. Luxoft’s software development services consist of core and mission critical custom software development and support, product engineering and testing, and technology consulting. Luxoft’s solutions are based on its proprietary products and platforms that directly impact its clients’ business outcomes and efficiently deliver continuous innovation.

Similar Posts

  • Latest New School Construction Update

    Next week (March 19 to March 23), Superstructure work will continue at the 8th floor level. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    The following week (March 26 to March 30), we will continue superstructure concrete and slabs on the 8th and 9th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    This weekend the site will be open on Saturday, March 17th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

    In addition, tomorrow, Friday the 16th, we will be starting operations at 6am in anticipation of a large concrete pour and will more than likely, with notification of the Department of Buildings, be going later into the evening to finish. Also on the weekend of the 10th the 14th St. Con Ed Vault utility connection street work will continue per DOT Permit granted for weekends only.

  • The Fourth Ave. Hotel

    You may have noticed construction work speeding along at the corner of 13th St. and 4th Ave. This is to be an 11-story, 162-room hotel in the medium price range. It’s being built by Sam Chang, the king of New York hotel development. He’s famous for finding ways to squeeze hotels onto tiny lots. In this case he’s keeping the facade of the former building as a kind of pedestal. Unusually sensitive for a developer who is usually accused of having no architectural taste whatsoever.