Latest New School Construction Update

Next week (July 22 to July 26), material and equipment deliveries and installation work will continue on all floors inside the building. Asphalt work on 14th st will begin this week to tie in the finished sidewalk. We will be opening the new sidewalk on 13th st. Additionally we will be working on the roofs of the building. Furniture deliveries will take place in the afternoon along 5th ave.

The following week (July 29 to August 2), material, equipment and furniture deliveries and installation work will continue on all floors as well as sidewalk work.

This weekend the site will be open on Saturday, July 20th for interior, roof, and sidewalk activities between the work hours of 7AM and 5PM as permitted by the City.