Weed Dispensary on the Way

If there was any doubt about the national momentum on legalized marijuana use in America, consider this. There will be a medicinal marijuana dispensary off Union Square come January 2016. The dispensary on 14th Street between Second and Third Avenues will be run by Columbia Care, a New York City-based company that was awarded one of the state’s five licenses to open a medicinal marijuana shop. The selections were made in July, and companies are moving forward on grand openings.

Similar Posts

  • 14th St. Busway Is Coming in January

    With the forthcoming 15-month L train shutdown edging closer, the MTA and the city’s Department of Transportation have decided to convert Manhattan’s 14th Street into a busway three months ahead of the April 2019 shutdown.

    The two agencies will launch the M14 Select Bus Service on January 6, 2019, in hopes that riders will give it a test-run before the actual shutdown begins. “By implementing the M14 SBS months before we start the L train tunnel repairs, we hope that customers will take the opportunity to try our buses and see how the 14th Street busway can factor into their commutes once we start work fixing the L train tunnel,” said New York City Transit President Andy Byford.

    Between 5 a.m. and 10 p.m., 14th Street between Ninth and Third avenues eastbound and Third and Eighth Avenues westbound will be restricted to bus traffic only. The new SBS route will complement the current M14A and M14D buses and combined, the three routes will be able to handle roughly 84,000 passengers per day, notes amNY.

    The SBS route will start off with five stops between First and Tenth avenues that match up with subway transfer points and will run every two minutes during morning and evening rush hours. After its initial launch, the SBS route will be extended east to the planned Stuyvesant Cove ferry terminal on the East River to accommodate ferry customers from Brooklyn. This is expected to happen shortly before the beginning on the shutdown.

  • Latest New School Construction Update

    Next week (January 9 to January 13), Superstructure work will continue at and 2nd , 3rd and 4th floor levels. The sidewalk shed along 14th Street has been opened and we will begin working on the side walk shed along 5th ave.

    The following week (January 16 to January 20), we will continue superstructure concrete and slabs on 2nd , 3rd and 4th floor levels. The weekend of Saturday 1/14/12 we will be installing a new crane that will service the site for the duration of the job.

    This weekend the site will be open on Saturday, January 7th, for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.