More Vegetarian Burgers

PLNT Burger has opened at 149 4th Ave. It’s the second veggie burger joint to open in the neighborhood in six months.

Similar Posts

  • Latest New School Construction Update

    Next week (October 10 to October 14), contractors will continue to excavate earth and load out material. Concrete foundation walls at the South East corner of the site and slab on grade work will continue. Underground electrical and plumbing work will continue. DOT approved street connections to underground utilities on Fifth Avenue will progress. Formwork and rebar for superstructure will continue at cellar levels.

    The following week (October 17 to October 21 ), we will continue superstructure concrete and slabs, street utility connections and underground electrical and plumbing.

  • When Macy’s Was Our Neighbor

     

    Here’s a 1910 view of the south side of 14 St. looking east from 6th Ave. from what was then the platform of the elevated train. As you can see, Macy’s was headquartered there (where Urban Outfitters is now) and expanded along the block over time as it grew. Eventually, the cobbled-together space got too complicated and the store decamped for its massive new digs in Herald Square. If you look closely at this building today, you can still see vestiges of Macy’s red star icon in a few places.

  • Latest New School Construction Update

    In response to community concerns about the time in the evening we end our concrete placing, DOB has granted our request to start placing our concrete at 6am, which will allow us to finish this work earlier in the evening. We have 8 more instances like this until we finish our superstructure in early June.

    Therefore next week (April 16 to April 20), Superstructure work will continue at the 13th and 14th floor levels. Wednesday, April 18th, we will have an identical pour with a 6 am start time and similar end time, weather permitting. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    The following week (April 23 to April 27), we will continue superstructure concrete and slabs on the 15th and 16th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    This weekend the site will be open on Saturday, April 14st for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

    In addition to the normal work on the job site, the 14th St. Con Ed Vault utility connection street work will continue per DOT Permit granted for weekends only.

  • Lovely View of Our Block: 1911

    index

    This view shows the east side of 5th Ave. at 13th St. in 1911. In other words, it’s where the New School now has its main entrance. Down the block on 13th St. you can see the tallish building that is now apartments. Ah, the good old days. Note that even in 1911, those elegant brownstones had seen better days. Since then, three large buildings have stood on this block, so that’s one reinvention about every 35 years.

    Credit: New York Public Library Digital Collection.