Latest New School Construction Update
ByDonNext week (July 9 to July 13), Mechanical equipment and work will continue at the 17th and 18th floor levels. Curtain wall will continue to be installed on the building. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.
The following week (July 16 to July 20), we will be working on the machine room levels on the 17th and 18th floors. Curtain wall will continue to be installed on the building. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.
This weekend the site will be open on Saturday, July 7th for superstructure activities as well as the demobilization of the crane from the site. In order to facilitate this effort we will be closing 13th street for the day to pedestrian and automotive traffic. Site work will begin at 6AM as permitted by the City. To control noise levels within the site, work activities will be limited to working on the mechanical systems of the building and using the crane and equipment to support activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.
Now Open: Aesop
ByDonOn University near 10th…the most expensive personal grooming products on Earth.
New Escalator in Subway Station
ByDonThe MTA is still chipping away at improvements on the L train, having announced a new escalator coming into service at the Union Square station to service the 19,000 pre-pandemic riders that shuffle on and off the platform every hour during the week.
This installation, designed to ease congestion through the busy interchange, follows elevators paired with a new entrance to the L train’s First Avenue station near Avenue A and switch replacements on the 4-5-6 near Union Square in recent months.
These improvements were funded by the MTA prior to the financial crisis they currently face due to COVID-19.
“This new escalator is another achievement for the larger L project team that, delivered that huge project early and below budget,” MTA Chief Development Officer Janno Lieber said. “Even in the midst of the COVID-19 pandemic we’re using innovative strategies to deliver customer improvements faster and at lower cost than ever before.”