  • Latest New School Construction Update

    Next week (January 30 to February 3), Superstructure work will continue at and 3rd, 4th and 5th floor levels.

    The following week (February 6 to February 10), we will continue superstructure concrete and slabs on 4th and 5th floor levels.

    This weekend the site will be open on Saturday, January 28th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

    In addition to the normal work this Saturday we will be disassembling the small crane and removing it from the site. During the demobilization 13th St. will be closed as well as some lanes on 5th Ave. Pedestrian traffic will also be temporarily closed on the east side of 5th ave. for safety.

    Please do not hesitate to contact me if you have any concerns or questions. Thank you

    Jane R. Crotty
    Senior Vice President
    George Arzt Communications, Inc.
    123 William Street, 22nd Fl.
    New York, NY 10038
    T (212) 608-0333

  • Latest New School Construction Update

    Next week (October 21st to October 25th), material and equipment deliveries and installation work will continue on the academic floors inside the building and we anticipate paving on 5th Ave.

    The following week (October 28th to November 1st), material and equipment deliveries and installation work will continue on academic floors.

    This weekend the site will be open on Saturday, October 19th for interior activities between the work hours of 7AM and 5PM as permitted by the City.