New School Construction: More of the Same
ByDonThis week (June 6-10), contractors will continue to excavate earth and rock, and load out material. We will complete the underpinning of the adjacent buildings. Installation of rakers, line drilling, lagging and sheeting around the perimeter will progress as well. Concrete foundation walls are scheduled to begin.
The following week, we will continue line drilling, rock excavation, and loading out, as well as lagging and sheeting.
Concrete foundation walls will progress.
Summer on the Sidewalk
ByDonIt’s at this time of the year that street life returns to our sidewalks, and with it comes litter, especially on 13th St., where fans of Joe Coffee linger on our stoop, smoke up a storm, and drop their butts. Such is life in the big city. The big problem with this is that we sometimes get sanitation tickets that aren’t our fault. The Board of Directors has a very cordial relationship with Joe’s owner, Jonathan Rubenstein, who is a good guy and a great example of a successful local entrepreneur fighting off the big chains. He’s busy expanding his empire, but he does care and responds to our complaints. In the meantime, feel free to remind visitors to our stoop not to drop their trash, and if you have the time, call 311 to complain because city inspectors will get Joe’s attention.
Park Renovation Continues Apace
ByDonIn Union Square Park, the 16th Street transverse and eastern plaza are now open to pedestrians, complete with additional park benches along the north sides of the transverse. New asphalt pavers and crushed bluestone allow the stately elm trees along the transverse to thrive while removing the previous trip hazard, and the entrance to the center lawn is now accessible to wheelchairs. The park’s new and expanded 15,000-square-foot play space is nearing completion with Parks Department final site inspections scheduled in the next few weeks. Soon, area kids will have endless hours of fun in this creative, colorful and beautifully landscaped play space designed by Michael Van Valkenburgh Associates. The North End Project is 91% complete and the remainder of the project, including new restroom facilities and the Pavilion, are expected to be finished by the end of the year.
Zen Palate Is Back
ByDonWalk down East 18th St. east of Park Ave. and you’ll see a new Zen Palate on your left. Welcome back!
Reminder: Annual Meeting on Wednesday, Oct 12
ByDonSee your mail or e-mail to get the Zoom log in information for this year’s annual shareholder’s meeting on Wednesday, October 12 at 7 PM.
Latest New School Construction Update
ByDonNext week (October 14th to October 18th), material and equipment deliveries and installation work will continue on the academic floors inside the building.
The following week (October 21st to October 25th), material and equipment deliveries and installation work will continue on academic floors.