Earth Day 1970 in Union Sq.

Go here to see a photo of the first Earth Day in Union Square, April 22, 1970. In the photo you can even see a bit of our building.

Similar Posts

  • Reyna Update

    On October 26, the owners of the upcoming Reyna restaurant, which is taking over the Le Midi space on 13th St., held an introductory Zoom call. Attendance was sparse, but it was interesting to hear their plans and to have the chance to voice concerns pre-emptively.

    The restaurant will likely be open until 11 on weekdays and midnight on weekends. It is meant to be an upscale drinking/dining experience, not a noisy bar. They will also be using the Karaoke Cave space as a site for “French Karaoke” as well as sort of a holding space for people who may be waiting for a table (a problem Le Midi certainly never had).

    They also plan to build a street-side dining shed, most of which will occupy the space now being used by Corkbuzz.

    In general, they seemed quite eager to hear about any issues that nervous neighbors like us might have ahead of time, rather than deal with our anger later. They hope to open in the March/April time frame.

    You can get an idea of what Reyna will be like by visiting the Web site for their two locations in Toronto:  www.barreyna.com 
    If you have any questions, you can contact them directly:

    Nicki at nicki@barreyna.com
    Etienne at 646-421-4242.

  • Latest New School Construction Update

    Next week (August 20 to August 24), Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on upper floors will continue and lower levels will continue on 13th st. with the aid of a small crane. The crane will remain on 13th st. for the purpose of curtain wall installation.

    The following week (August 27 to August 31) Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation will continue on all floors. Work on 13th st should be complete by the end of this week and will be moved to 5th ave. to continue wrapping the building.

    This weekend the site will be open on Saturday, August 25th for superstructure related activities and curtain wall installation between the work hours of 7AM and 5PM as permitted by the City. The crane on 13th st. will not be used during the weekend. Con Ed is on site working on the building but is not in any of the streets.

    Additionally over the holiday weekend the site will be open on Saturday, September 1st but will be closed on Monday, the 3rd.

  • Latest New School Construction Update

    Next week, 03/11/2013 – 03/15/2013 Material and equipment deliveries and installation work will continue on all floors inside the building. Roof work, work on the new sidewalks around the building, dismantling of the exterior construction hoist and related exterior building work will also continue.

    The following week, 03/18/2013 – 03/22/2013 Material and equipment deliveries and installation work will continue on all floors and roofs. Sidewalk work and dismantling of the exterior construction hoist and related exterior work will also continue.

    We anticipate the take down of the 14th Street sidewalk shed to begin within the next 2 weeks.