New School Construction Update

The latest from the New School:

Next week (January 17-21), Urban Foundations will continue to drill solder piles on 14th Street. The pile driving rig is scheduled to arrive on site, and will begin driving piles on 5th Ave, moving South. Loading out of debris and earth from the site will continue. Hand chopping of the existing foundation wall in the South East corner of 65 Fifth will also be taking place. Installation of the fence along the USC Courtyards will take place, followed by the removal of the existing protection.

The following week (January 23 – 28), Urban is anticipated to continue driving piles along 5th Avenue, then continuing to 13th Street moving East. Excavation of earth and installation of timber lagging between piles on 14th street is planned to begin. Loading out of debris and earth from the site will continue. Demolition of existing foundation wall in SE corner of 65 Fifth by hand chopping will continue.