Latest New School Construction Update

DOB has granted our request to start placing our concrete at 6am, which will allow us to finish this work earlier in the evening. We have 5 more instances like this until we finish our superstructure in early June.

Therefore next week (April 23 to April 27), Superstructure work will continue at the 14th and 15th floor levels. Monday, April 23rd, and Thursday, April 26th, we will have a pour with a 6 am start time and similar end time, weather permitting. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

The following week (April 30 to May 4), we will continue superstructure concrete and slabs on the 15th and 16th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

This weekend the site will be open on Saturday, April 21st for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

In addition to the normal work on the job site, we will have an additional crane on site at 13th st. and 5th ave. to install the stair trusses on the west side of the building. The crane will be completely on site and should not interfere with pedestrian or automotive traffic in the area.

Similar Posts

  • Latest New School Construction Update

    Next week (October 14th to October 18th), material and equipment deliveries and installation work will continue on the academic floors inside the building.

    The following week (October 21st to October 25th), material and equipment deliveries and installation work will continue on academic floors.

    This weekend the site will be open on Saturday, October 12th for interior activities between the work hours of 7AM and 5PM as permitted by the City.

  • Latest New School Construction Update

    This is the 2 week look ahead for the New School’s University Center. Next week (August 5 to August 9), material and equipment deliveries and installation work will continue on all floors inside the building.

    The following week (August 12 to August 16), material and equipment deliveries and installation work will continue on all floors.

    This weekend the site will be open on Saturday, August 3rd for interior, and sidewalk activities between the work hours of 7AM and 5PM as permitted by the City. Additionally we will be paving along 13th st.

    Just a note to those who have made inquiry, the wall board panels are temporary and will be replaced when the final entrances are installed.

  • Yet Another Construction Update from the New School

    Next week (August 15 to August 19), contractors will continue to excavate earth and rock, and load out material. Installation of bracing rakers, line drilling, lagging and sheeting around the perimeter will progress as well. Concrete foundation walls will continue along the perimeter of the site. Interior core foundation work will proceed. The following week (August 22 to August 26 ), we will continue with concrete foundation walls, line drilling, rock excavation, loading out, and interior core foundation work & underground plumbing. DEP will continue to work on the water main along 13th Street. The site will be open on Saturday, August 13th. Work hours are between 9AM and 5PM as permitted by the City. To control noise levels, work activities will be limited to the placement of formwork and rebar for concrete placement, wood lagging, and installation of walers and braces. There will be no rock excavation, rock chopping, or hauling on Saturday.