Latest New School Construction Update

Next week (May 21 to May 25), Superstructure work will continue at the 18th floor level. The superstructure concrete work will be completed on the building buy the end of the month. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

The following week (May 28 to June 1), we will be working on the machine room levels on the 18th floor. Additionally we will have another crane on the Northwest corner of the site to help with a steel truss installation. This should not greatly affect pedestrian or road traffic. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic. The site will be closed on Monday, May 28th for the Memorial Day Holiday.

This weekend the site will be open on Saturday, May 19th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City.

To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise. In addition to the normal work there will be a crew on 14th st. working on the Con Ed site connections.

Similar Posts

  • Latest New School Construction Update

    Next week (August 12 to August 16), material and equipment deliveries and installation work will continue on all floors inside the building. New School Students will be moving into the building starting August 15th and will continue gradually through the end of August.

    The following week (August 19 to August 23), material and equipment deliveries and installation work will continue on all floors.

    This weekend the site will be open on Saturday, August 10th for interior, and sidewalk activities between the work hours of 7AM and 5PM as permitted by the City.

  • Artist Will Go Homeless to Draw Attention to Homelessness

    A Queens man is hoping to turn sleeping on the streets into big bucks for the homeless.

    Yusef Ramelize, a 33-year-old graphic designer, will leave his Ozone Park apartment Sunday and take up residence in Union Square Park. He won’t shower and he won’t have shelter during his “Homeless for One Week” project.

    “My reasoning for doing this is to inspire people to make sacrifices within their own lives,” Ramelize said of his project, now in its second year.

    He raised $3,635 in March 2009 and donated it to the Coalition for the Homeless. This year’s beneficiary will be the Food Bank of New York.

    Ramelize will hand out flyers and keep a videotaped diary of his experiences in order to help elicit donations on his website, homelessforoneweek.com.

    “It’s really about me pushing myself to see how much of a sacrifice I’m willing to make every year to get the word out,” Ramelize said.

    Ramelize chose Union Square to pay homage to his biggest inspiration, Mohandas Gandhi, who is immortalized with a statue on the west side of the park.

    “That’s one of the reasons I did it here,” Ramelize admits. “He wanted to bring peace around him, and he was willing to sacrifice his life.”

    As if braving the elements for seven days wasn’t enough, the slender Ramelize will also be fasting from sunrise to sunset for the Muslim holy month of Ramadan.

  • Latest New School Construction Update

    Next week (January 28 to February 1), material and equipment deliveries and installation work will continue on all floors inside the building as well as roof work. Additionally we will begin work on the new sidewalks around the building.

    The following week (February 4 to February 8), Material and equipment deliveries and installation work will continue on all floors and roofs as well as sidewalk work.

    This weekend the site will be open on Saturday, January 26th for interior, superstructure and sidewalk related activities between the work hours of 7AM and 5PM as permitted by the City.

  • See the Plans for the new New School

    An invitation from the New School to attend a preview of the new building on May 6:

    April 26, 2010

    To Our Neighbors, To meet the university’s evolving needs, plans for the construction of a new University Center at 65 Fifth Avenue will continue to move forward this summer. Because The New School has made it a priority to engage the entire university in the project’s development, we invite you to view the next phase of building design at a second exhibition featuring an overview of the current plan. We will also have a model of the building on display. Please join us on May 6 from 3:30 p.m. to 5:30 p.m. in the Theresa Lang Community and Student Center on the second floor of 55 W. 13th Street. This open house will include new renderings of the building design, academic and social spaces, sustainability systems, and details about the construction schedule. As in the past, attendants will be able submit comments and ask questions of many of the principals, including New School staff, architects and professionals from the design firm and construction trades. We hope to see you there.