Latest New School Construction Update

Next week (July 16 to July 20), Mechanical equipment deliveries and work on them will continue at the 17th and 18th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue. Curtain wall installation will continue.

The following week (July 23 to July 27), we will be working on the machine room levels on the 17th and 18th floors. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

This weekend the site will be open on Saturday, July 14th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

Similar Posts

  • A Memo from The New School

    Here’s what’s happening in their building as described in a memo sent to the university community:

    June 22, 2009
    From President Bob Kerrey and Provost Tim Marshall Abatement of Hazardous Materials in the University Center at 65 5thAvenue This is a follow-up to the recent announcement of the closing of the 65Fifth Avenue. There were some questions from members of our communityand we thought it would be helpful to provide additional information. The closing occurred because our university’s trustees have approvedthe removal and abatement of hazardous materials in the building.Several Board members with considerable New York City constructionexperience recommended that abatement work be started in advance of thedecision to build since it is highly likely that decision will be madethis fall. Abatement of hazardous material will shorten the duration ofthe construction of the University Center project. However, becauseabatement results in stripping the interior of the building of allfinishes, it was necessary to close the building in order to performthis work. Please note that the abatement work would have beennecessary regardless of future building plans. The Board had previously authorized the production of schematicdrawings for a new building. This authorization has led to extensivecollaboration with the newly created University Facilities Committee.This committee is working closely with the architect, and severalsubcommittees have been formed to offer input around particular kinds ofspaces. This input will likely lead to a final Board decision in the fall toproceed with construction of the Fifth Avenue University Center. Thisdecision will depend upon evaluation of new construction cost estimates,of actual enrollment results, and of financing. We recognize that the closing of the 65th Fifth Avenue has resulted insignificant dislocation of student activities. We have accommodated someof these activities with new construction in Arnhold Hall on 13thStreet. However, more needs to be done. We are pursuing severalpromising real estate opportunities that give us confidence that we willbe able to provide the new amenities this year. In the unlikely event adecision is made not to proceed with the new construction, or to delayconstruction for a long period of time, the trustees will review alloptions for dealing with the existing building at 65 Fifth Avenue. We expect that a schedule of construction activities at the site can beannounced within a couple of weeks, when we expect the abatement anddemolition contracts approved by the trustees to be finalized. Afterworking with the University Facilities Committee to reach broadconsensus about the program for the new building, we will continue tomeet throughout the summer with the Committee and with other user groupsin developing the schematic design. We are also working to set upvenues for regular communication to the entire University communityabout the project’s progress.

  • Latest New School Construction Update

    Next week (February 25 to March 1), material and equipment deliveries and installation work will continue on all floors inside the building as well as roof work. Additionally we will begin work on the new sidewalks around the building. We have begun dismantling the construction hoist on the building exterior and will continue to do so for the upcoming weeks.

    The following week (March 4 to March 8), material and equipment deliveries and installation work will continue on all floors and roofs as well as sidewalk work.

    This weekend the site will be open on Saturday, February 23rd for interior, superstructure, sidewalk, and hoist removal related activities between the work hours of 7AM and 5PM as permitted by the City.

  • Farmer’s Market Winter Warriors

     

    An update from the Farmer’s Market:

    The time has come to flex your Winter Warrior muscles! Each year, from January through March, Greenmarkets across the city participate in the Winter Warrior Challenge. If you shop at the market during the coldest months of the year, you can win a prize (and Winter Warrior bragging rights!)!

    It’s simple to participate and fun for the whole family! All you need to do is stop by any Greenmarket Market Info Tent to pick up your Winter Warrior card. Then, every time you shop at the Greenmarket between January and March, visit the Info Tent to get your card stamped.

    Shop ten times before March 31st and win a small Greenmarket prize plus an entry into our raffle for one of our grand prizes. For details, grand prize announcements, and more, follow us at @unsqgreenmarket on Instagram!