Latest New School Construction Update

Next week (November 12 to November 16), Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on the lower floors will proceed along 14th st. inside the construction site. The crane that is on site will remain for the duration of curtain wall installation and will not affect pedestrian or automotive traffic.

The following week (November 19 to November 23) Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on the lower floors will proceed along 14th st. inside the construction site. The site will be closed on November 22 for the holiday.

This weekend the site will be open on Saturday, November 17th for superstructure related activities and curtain wall installation between the work hours of 7AM and 5PM as permitted by the City. Con Ed will be working in the street.