Latest New School Construction Update

Next week (October 29 to November 2), Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on the lower floors will proceed along 14th st. inside the construction site. The crane that is on site will remain for the duration of curtain wall installation and will not affect pedestrian or automotive traffic.

The following week (November 5 to November 9) Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on the lower floors will proceed along 14th st. inside the construction site.

This weekend the site will be open on Saturday, October 27th for superstructure related activities and curtain wall installation between the work hours of 7AM and 5PM as permitted by the City. Con Ed will be working in the street.

Similar Posts

  • 9 East 13th St. in 1939, Part IV

    Thanks to Charles Stimson for purchasing and sharing these four photographs from the city archives. Shot for a tax survey in 1939, they show our block and are full of fascinating detail if you click on them to blow them up and look a little closer. Wouldn’t you love to stop off at Marty’s Luncheon for a sandwich? As New York races into the future, it’s quite a thrill to be able to look back and remind ourselves how things used to be.

  • Seahorse, A New Restaurant on the Edge of the Park

    The renovated W Union Square Hotel now boasts a hot new restaurant that the New York Post loves:

    It took Seahorse, the new seafood spot in the W hotel, four years to open after it was first planned — and only two weeks to conquer Manhattan.

    The wonderful eatery from owner John McDonald and chef John Villa is a rare, instant artistic and commercial success that’s just what Union Square needed.

    The blocks around the park lost their culinary cred after Brazilian-style Coffee Shop closed in 2018 and Blue Water Grill a year later, leaving the famous Greenmarket its only claim to glory. Seahorse, on Park Avenue South at East 17th Street, puts the juice back. The corner will be even more of a food destination when a giant STK Steakhouse opens soon across the street.

    McDonald’s Mercer Street Hospitality owns a half dozen crowd-pleasing eateries including Bowery Meat Company, Bar Mercer and, most famously, Lure Fishbar in Soho, which might lose its home of 20 years to Prada.

    Seahorse tops them all. The stunning design by David Rockwell offers everyone open views of the sea of booths, banquettes and tables. Nautical blue trim sets the theme. Walls of rich teak refer to, but don’t copy, Lure and its yacht cabin vibes.

    Villa is equally at home in corporate and individual-restaurant settings. He was recently culinary head of Tao Group, but I remember him as well for Pico — a great modern-Portuguese restaurant that didn’t survive Tribeca’s street closings after 9/11.

  • Latest New School Construction Update

    DOB has granted our request to start placing our concrete at 6am, which will allow us to finish this work earlier in the evening. We have 5 more instances like this until we finish our superstructure in early June.

    Therefore next week (April 23 to April 27), Superstructure work will continue at the 14th and 15th floor levels. Monday, April 23rd, and Thursday, April 26th, we will have a pour with a 6 am start time and similar end time, weather permitting. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    The following week (April 30 to May 4), we will continue superstructure concrete and slabs on the 15th and 16th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    This weekend the site will be open on Saturday, April 21st for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

    In addition to the normal work on the job site, we will have an additional crane on site at 13th st. and 5th ave. to install the stair trusses on the west side of the building. The crane will be completely on site and should not interfere with pedestrian or automotive traffic in the area.