Latest New School Construction Update

Next week (September 24 to September 28), Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on the upper floors will continue. Curtain wall installation on the lower floors will proceed along 5th ave inside the construction site. The crane that is on site will remain for the duration of curtain wall installation and will not affect pedestrian or automotive traffic.

The following week (October 1 to October 5) Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation will continue on all floors.

This weekend the site will be open on Saturday, September 22nd for superstructure related activities and curtain wall installation between the work hours of 7AM and 5PM as permitted by the City. Con Ed is on site working on the building but is not in any of the streets.

Similar Posts

  • Thai, Thai Again?

    We’ve had Thai restaurants as downstairs neighbors before, and now a new one may be coming to replace Corkbuzz at 13 East 13th. A liquor license application has been filed by Varith, a “family-run” Thai restaurant that has a highly regarded sister operation called Valla Table in Hell’s Kitchen run by Chuck Valla, who was a private chef prior to opening this first place in 2021. Looks good.

  • Latest New School Construction Update

    Next week (February 6 to February 10), Superstructure work will continue at and 4th and 5th floor levels. The following week (February 13 to February 17), we will continue superstructure concrete and slabs on 4th, 5th and 6th floor levels.

    This weekend the site will be open on Saturday, February 4th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

    14th Street Con ED vault utility connection street work will continue per DOT Permit granted for weekends only.