The Upcoming 14th St. Busway

For 17 hours each day during the L train shutdown, Manhattan’s 14th Street will be converted into a “busway” with very limited access to car traffic, reports the NY Daily News.

According to court documents from the MTA from a lawsuit regarding the shutdown, 14th Street, from Ninth to Third avenues eastbound and from Third to Eighth avenues westbound, will give priority to bus traffic from 5 a.m. to 10 p.m., seven days a week in attempt to mitigate transit woes. Manhattan residents will be granted vehicle access to 14th Street for pickups and drop-offs only.

Additionally, the Department of Transportation has revised its bike path plan, now calling for two one-way bike baths on 12th and 13th streets instead of a single two-way bike path on 13th Street, notes the Daily News.
“We’re solving, hopefully, the local mobility and access challenge while discouraging through traffic on 14th Street,” said DOT Commissioner Polly Trottenberg in a statement.

Last week, City Council speaker Corey Johnson announced plans to propose new legislation that would require the city to open at least two information centers to update riders about the progress of the Canarsie Tunnel repairs, give transportation alternatives, and create an ombudsman job within the Department of Transportation to monitor comments and investigate complaints about transportation projects.

Similar Posts

  • Lastest New School Construction Update

    Next week (November 14 to November 18), DOT approved street connections to underground utilities on Fifth Avenue and 13th street will continue. Superstructure work will continue at cellar, 1st, and 2nd floor levels. A street crane will be moved into position early on Wednesday the 11/16 on 13th street to place structural steel in the building and should be out by the end of the day, weather pending.

    The following week (November 21 to November 25), we will continue superstructure concrete and slabs. Street utility connection work will continue. Sidewalk sheds will continue being erected around the perimeter of the site. The project will be closed on Thanksgiving Day, 11/24, and open for work on 11/25.

    This weekend the site will be open on Saturday, November 12th for superstructure related activities between the work hours of 9AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork, plumbing and electrical work, rebar for concrete placement and use of the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

  • Too Close for Comfort

    The New York Post reports this robbery just one block away:

    A woman who left her Union Square apartment to check in on a 102-year-old neighbor returned to find a well-dressed burglar grabbing $50,000 worth of her jewelry, cops said yesterday.

    The thief — decked out in a black suit and tie — had sneaked into an apartment building on University Place at 3 p.m. Monday and was prowling around for an unlocked door when he hit the jackpot at Linda Kaplan’s home, sources said.

    As the thief was stashing bling in a canvas bag, Kaplan, 76, walked in.

    She demanded to know what he was doing, and he responded, “I’m with the Fire Department,” according to cops.

    When Kaplan demanded to see ID, the 6-foot-2 bandit threw her down.

    “He grabbed my shoulders and pushed me to the ground,” Kaplan said. “I grabbed his legs. I tried to stop him from leaving.

    “Once he knocked me down, I started screaming for help.”

    Among those who ran to her aid was a painter working in an apartment upstairs. Minutes earlier, the thief had poked his head in that unit but fled when he saw the worker.

    Cops said the bandit operated like an “office creeper,” a well-dressed thief who looks for laptop computers or purses at unoccupied office desks.

  • Latest New School Construction Update

    Next week (June 4 to June 5), Superstructure work will continue at the 18th floor level. The superstructure concrete work will be completed on the building buy the end of the month. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    The following week (June 11 to June 15), we will be working on the machine room levels on the 18th floor. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic. The crane on site will be demobilized and removed from site at the end of June.

    This weekend the site will be open on Saturday, June 2nd for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.