Restaurant Devastation Continues
They are dropping like flies. Goodbye to Nanoosh, Nix, Blue Stripes, Le Midi (in our building) Le Maison de Croque Monsieur, and more. What will replace them?
Next week (February 18 to February 22), material and equipment deliveries and installation work will continue on all floors inside the building as well as roof work. Additionally we will begin work on the new sidewalks around the building. The sidewalk shed on 14th st. is scheduled to begin dismantling, pending construction progress. The site will be closed on Monday, February 18th, for the holiday.
The following week (February 25 to March 1), Material and equipment deliveries and installation work will continue on all floors and roofs as well as sidewalk work.
Curious about how the renovation of Union Square is proceeding? The Villager has all the details here. The bottom line: on schedule.
Sausage Inc. has opened the doomed space on University between 12th and 13th that has housed a bakery, a Philly Cheesesteak shop and Wok New York.
Next week (June 4 to June 5), Superstructure work will continue at the 18th floor level. The superstructure concrete work will be completed on the building buy the end of the month. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.
The following week (June 11 to June 15), we will be working on the machine room levels on the 18th floor. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic. The crane on site will be demobilized and removed from site at the end of June.
This weekend the site will be open on Saturday, June 2nd for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.
Next week (June 25 to June 29), Mechanical equipment and work will continue at the 17th and 18th floor levels. The superstructure concrete work will be completed on the building by the end of the month. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.
The following week (July 2 to July 6), we will be working on the machine room levels on the 17th and 18th floors. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic. The crane is scheduled for demobilization on Saturday the 7th.
Read all about the sales difficulties of 61 5th Avenue and see lots of pictures here.