Agata and Valentina Building Slated for Demolition?

This report from Greenwich Village Society for Historical Preservaation notes that 64 University Place, the non-descript building currently housing Agata and Valentina, may be scheduled to meet its destiny with the wrecking ball. In its place, a 12-story building.

Village Preservation has learned that a developer has filed plans to demolish 64-66 University Place (10th/11th Street) within our proposed South of Union Square Historic District we have been fighting to get landmarked.

No permits have yet been filed for a new building, though we understand a 12-story building is being contemplated. The zoning for the site allows a roughly 42,000 square foot building here, of residential, commercial, and community facility uses, with about 6-7,000 square feet of additional air rights purchased from neighboring 70 University Place. By comparison, neighboring 21 East 10th Street is approximately 56,000 square feet.

Village Preservation has been campaigning for landmark designation for this area, and our research and documentation submitted to the City shows that this building, in spite of its utilitarian looks, actually has an incredibly important history worthy of recognition and protection. While we have made some progress recently advancing our landmarking proposal, the City has nevertheless resisted landmarking the full proposed district, and Councilmember Carlina Rivera, who represents this area, has not endorsed the historic district landmarking proposal.

Similar Posts

  • New School Construction Update

    The latest from the New School:

    Next week (January 17-21), Urban Foundations will continue to drill solder piles on 14th Street. The pile driving rig is scheduled to arrive on site, and will begin driving piles on 5th Ave, moving South. Loading out of debris and earth from the site will continue. Hand chopping of the existing foundation wall in the South East corner of 65 Fifth will also be taking place. Installation of the fence along the USC Courtyards will take place, followed by the removal of the existing protection.

    The following week (January 23 – 28), Urban is anticipated to continue driving piles along 5th Avenue, then continuing to 13th Street moving East. Excavation of earth and installation of timber lagging between piles on 14th street is planned to begin. Loading out of debris and earth from the site will continue. Demolition of existing foundation wall in SE corner of 65 Fifth by hand chopping will continue.

  • New School Construction Update

    This week (May 16 to May 20), Contractors will continue to excavate earth and rock, and load out material. We will continue to underpin the 13th Street adjacent building. Drilling of tie-backs, installation of rakers, line drilling, lagging and sheeting around the perimeter will progress as well. Preparation for concrete foundation walls is scheduled to begin.

    The following week (May 23 to May 27), we will continue line drilling, rock excavation, and loading out as well as, lagging and sheeting. Concrete foundation walls will progress.

  • Latest New School Construction Update

    Next week (February 13 to February 17), Superstructure work will continue at 5th and 6th floor levels.

    The following week (February 20 to February 24), we will continue superstructure concrete and slabs on the 5th and 6th floor levels.

    This weekend the site will be open on Saturday, February 11th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise. Additionally 14th St. Con Ed Vault utility connection street work will continue per DOT Permit granted for weekends only.