  • Reminder: Shareholders’ Meeting

    The annual shareholder’s meeting will take place on Wednesday June 30th at 7PM at the Seafarers’ and Interational House at 123 East 15th St, second floor.

    At the meeting, the Board of Directors will be seeking at least one new member. If you wish to become a candidate for the Board and have your name placed on the ballot, please feel free to provide a short biography of yourself via fax (212) 986-0002 or e-mail to ymartinez@akam.com. The Board will also welcome nominations at the meeting itself.

  • New School Building Design Update

    As you’re well aware, the demolition and construction of The New School site at 65 Fifth Avenue is well underway. On Thursday, The New School revealed for the first time the official design of the building, which includes some of the elements from its earliest sketches, such as the exposed staircases, but is different in two notable ways: the building is smaller than originally planned, and it is partially class in brass, rather than entirely in glass.

    The building is being constructed as of right. There is no more debate over design or size. This is pretty much what we’re going to see: a university hub of about 16 stories with eight floors of campus space topped by a smaller eight floors of dormitory housing for 600 students.

    To get caught up on what the building looks like and see many photos of the model, click here.

    To read the somewhat positive New York Times architecture critic’s review, click here.

    A neighbor attended the public viewing of the model and came away with some great facts:

    –The loading dock is on 13th street at the eastern most corner of the lot.

    –The main entrance to the building is on the southwest corner. This is for everything except the dormitories.

    –The dormitory entrance is on 5th avenue, about 1/3 of the way down from 14th street.

    –The northern 1/3 of the building at street level is retail – no word on what though.

    –Directly above the retail is a cafeteria. It looks like seating for 300, which makes sense considering the 600 person dormitory.

    –The dormitory floors are set back on all sides, and shaped in a ‘C’ with a light well on the eastern side of the stack. They are four bed suites, with kitchenettes in them.

    –The set-back between the lower and upper halves is a green roof, and they say that for liability reasons it will not be open to the general building population. Pressing on this, and the answer was that while the green roof hasn’t been engineered yet, it is likely going to be possible to have foot traffic on it and will perhaps be open to supervised use (during a class, or for an experiment of some kind). (So no midnight keg parties, we hope.)

    The green roof is at the level of 7 East 13th St/10 East 14th St, so about the same height as our roof.

    — It looks like it’s designed to keep students inside the building, and not loitering on the street. The canopies are small, and the doors aren’t inset, so there isn’t any natural gathering space just outside on the sidewalk.

    We hope that this brings everyone up to date on a project that will be a big part of the pulse of the neighborhood for the next two years….and beyond.

  • Latest New School Construction Update

    In response to community concerns about the time in the evening we end our concrete placing, DOB has granted our request to start placing our concrete at 6am, which will allow us to finish this work earlier in the evening. We have 8 more instances like this until we finish our superstructure in early June.

    Therefore next week (April 16 to April 20), Superstructure work will continue at the 13th and 14th floor levels. Wednesday, April 18th, we will have an identical pour with a 6 am start time and similar end time, weather permitting. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    The following week (April 23 to April 27), we will continue superstructure concrete and slabs on the 15th and 16th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    This weekend the site will be open on Saturday, April 14st for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

    In addition to the normal work on the job site, the 14th St. Con Ed Vault utility connection street work will continue per DOT Permit granted for weekends only.