  • Latest New School Construction Update

    Next week (October 7 to October 11), material and equipment deliveries and installation work will continue on the academic floors inside the building. Additionally we will be using a lift on the sidewalk to wash the exterior of the building.

    The following week (October 14 to October 18), material and equipment deliveries and installation work will continue on academic floors.

    This weekend the site will be open on Saturday, October 5th for interior activities between the work hours of 7AM and 5PM as permitted by the City.

  • Latest New School Construction Update

    Next week (May 28 to June 1), Superstructure work will continue at the 18th floor level. The superstructure concrete work will be completed on the building by the end of the month. We will begin pouring concrete at 6am on Friday the 25th in order to finish in a timely manner. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic. The site will be closed on Monday, May 28th for the Memorial Day Holiday.

    The following week (June 4 to June 8), we will be working on the machine room levels on the 18th floor. Additionally we will have another crane on the Northwest corner of the site to help with a steel truss installation. This should not greatly affect pedestrian or road traffic. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

  • Latest New School Construction Update

    Next week (November 21 to November 25), DOT approved street connections to underground utilities on Fifth Avenue and 13th street will continue. Superstructure work will continue at cellar, 1st, and 2nd floor levels. Sidewalk sheds will continue being erected around the perimeter of the site. The project will be closed on Thanksgiving Day, 11/24, and open for work on 11/25 and 11/26, weather pending. The following week (November 28 to December 2), we will continue superstructure concrete and slabs. Street utility connection work will continue.