As construction continues at the northern end of Union Square Park, more and more trees are being removed. See for yourself.
Next week (June 4 to June 5), Superstructure work will continue at the 18th floor level. The superstructure concrete work will be completed on the building buy the end of the month. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.
The following week (June 11 to June 15), we will be working on the machine room levels on the 18th floor. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic. The crane on site will be demobilized and removed from site at the end of June.
This weekend the site will be open on Saturday, June 2nd for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.
First it was the mysterious India Pavillion, which survived for many years even though no one ever ate there. Then it was Mauricio for a couple of years. Now Da Andrea is thriving in the spot on West 13th formerly occupied by those two long gone establishments. People sure seem to like it.
Next week (September 23 to September 27), material and equipment deliveries and installation work will continue on the academic floors inside the building. Additionally we will be using a lift on the sidewalk to wash the exterior of the building.
The following week (September 30 to October 4), material and equipment deliveries and installation work will continue on academic floors.
This weekend the site will be open on Saturday, September 21st for interior activities between the work hours of 7AM and 5PM as permitted by the City.
Pop diva Rihanna was spotted singing karaoke downstairs at Shanghai Square. End of report.
Torch & Crown Beer Garden is back for its third season in the Union Square Park Pavilion, serving up locally brewed beers and fan favorites like the Lou Burger, pizza, and pretzels.
From now through early November, enjoy: