The Latest New School Construction Update

This week (May 23 to May 27), Contractors will continue to excavate earth and rock, and load out material. We will complete the underpinning of the adjacent buildings. Installation of rakers, line drilling, lagging and sheeting around the perimeter will progress as well. Concrete foundation walls are scheduled to begin.

The following week (May 30 to June 3), we will continue line drilling, rock excavation, and loading out, as well as lagging and sheeting.

Concrete foundation walls will progress.