Sausage Factory

What used to be Wok to Walk on University Place between 12th and 13th is now Sausage Inc. selling…sausages.

Similar Posts

  • Upcoming Event: Book Talk

    What: Hotel No Tell:
    A Book Talk by Daphne Uviller

    When:
    Monday, June 20
    6:30 – 8:00 P.M.
    Where: Jefferson Market Library 425 6th Avenue (btwn West 9th/10th Streets)
    Cost: free; reservations required
    RSVP: rsvp@gvshp.org or 212-475-9585 ext. 35

    Zephyr Zuckerman, the lovable, hapless heroine of Daphne Uviller’s Super in the City, is back. In Hotel No Tell, she’s armed and undercover as a concierge at a Greenwich Village hotel, tracking down a missing hundred grand. Please join third-generation Villager Daphne Uviller as she reads from Hotel No Tell which will be available for purchase and signing. (More information)

  • New School Construction Update

    This week (May 16 to May 20), Contractors will continue to excavate earth and rock, and load out material. We will continue to underpin the 13th Street adjacent building. Drilling of tie-backs, installation of rakers, line drilling, lagging and sheeting around the perimeter will progress as well. Preparation for concrete foundation walls is scheduled to begin.

    The following week (May 23 to May 27), we will continue line drilling, rock excavation, and loading out as well as, lagging and sheeting. Concrete foundation walls will progress.

  • New Plans for 65 5th Ave. to Be Revealed

    If you’re curious about the plans for the New School’s new construction on our block, there will be a public presentation on February 17. Here’s how the Greenwich Village Society for Historic Presentation is billing it:

    On Wednesday, February 17 at 6:30 pm The New School (TNS) will make a public presentation of its current plans for a new development at 65 Fifth Avenue, between 13th and 14th Streets. Having originally proposed a 300-350 ft. tall building rising straight up over the entire site which would have required several zoning variances, TNS is now proposing a much smaller, 16-story, 189 ft. tall (plus mechanicals) building which will set back above the 6th floor and which conforms to the existing zoning for the site. The presentation will be similar to that which was made to GVSHP, other community groups, and elected officials in December. The plans are not yet finalized at this time, but do contain significant details about TNS’ thinking and progress on the design.

    The fact that the mass and height of the proposed building has been reduced significantly from prior proposals in a very positive development. However, GVSHP does have concerns about the metal and glass design currently being contemplated for the facade of the building. The public presentation to Community Board #2’s Institutions Committee will be an opportunity to learn more about TNS’ plans for the site, ask questions, and provide feedback about the project.

    Attend the public presentation on Wednesday, February 17th at 6:30 pm at the St. Vincent’s Hospital cafeteria on 12th Street.