The Latest Construction Update

The New School says:

Next week (August 29 to September 2), Contractors will continue to excavate earth and rock, and load out material. Installation of bracing rakers and line drilling will progress as well. Concrete foundation walls will continue along the perimeter of the site. Interior core foundation work and underground electrical and plumbing will proceed. Contractors will be removing the interior earth ramp. A small cherry picker crane will be delivered to the site next week and will be stationed inside the Construction fence. This crane will remain there for approximately two months.

The following week (September 6 to September 9 ), we will continue with concrete foundation walls, line drilling, rock excavation, loading out, interior core foundation work, and underground electrical and plumbing. Concrete pours for the slab on grade are anticipated to start this week. The site will be closed for Labor Day weekend (Saturday, Sept. 3 through Monday, Sept. 5).

DEP will continue to repair the water main along 13th Street. As part of this work, the DEP may periodically shut water service off. This work is out of our control.

Similar Posts

  • Latest New School Construction Update

    Next week (July 2 to July 6), Mechanical equipment and work will continue at the 17th and 18th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic. The site will be closed on Wednesday, July 4th, for the holiday.

    The following week (July 9 to July 13), we will be working on the machine room levels on the 17th and 18th floors. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic. The crane is scheduled for demobilization on Saturday the 7th.

    This weekend the site will be open on Saturday, June 30th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to working on the mechanical systems of the building and using the crane and equipment to support activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.