The Latest Construction Update

The New School says:

Next week (August 29 to September 2), Contractors will continue to excavate earth and rock, and load out material. Installation of bracing rakers and line drilling will progress as well. Concrete foundation walls will continue along the perimeter of the site. Interior core foundation work and underground electrical and plumbing will proceed. Contractors will be removing the interior earth ramp. A small cherry picker crane will be delivered to the site next week and will be stationed inside the Construction fence. This crane will remain there for approximately two months.

The following week (September 6 to September 9 ), we will continue with concrete foundation walls, line drilling, rock excavation, loading out, interior core foundation work, and underground electrical and plumbing. Concrete pours for the slab on grade are anticipated to start this week. The site will be closed for Labor Day weekend (Saturday, Sept. 3 through Monday, Sept. 5).

DEP will continue to repair the water main along 13th Street. As part of this work, the DEP may periodically shut water service off. This work is out of our control.