  • Update on Tammany Hall Dome Construction

    Construction of the glassy turtle shell-shaped dome on top of Union Square’s landmarked Tammany Hall building is officially underway. The building at 44 Union Square, formerly home to NYC’s Democratic party machine, is being transformed into modern office and retail space. New construction photos provided to 6sqft show the start of the unconventional dome’s installation, with the diagonally intersecting glass and steel now visible from the street. The political organization of Tammany Hall formed in New York City in the late 18th century and helped Democrats control city and state politics for decades. After a few different headquarter locations, the society landed in a building on East 17th Street and Union Square. The International Ladies Garment Workers Union bought the building in 1943. Other tenants have included the New York Film Academy and the Union Square Theatre. Designed by BKSK Architects, the redevelopment project consists of a gut renovation and the addition of four stories of retail space in the building’s base, with three levels of office space on the upper levels, including inside the dome. The architects designed the glass dome as an ode to the turtle which Lenape Chief Tamanend stands upon on a Philadelphia statue. Tammany Hall was named after the leader. According to the firm, the dome is “meant to be both evocative and respectful of the building’s past while also bringing architectural spectacle to this rather staid corner of Union Square.” BKSK first submitted plans to revamp the historic building in 2014. After the project was approved a year later by the Landmarks Preservation Commission, developer Reading International secured $57.5 million in financing. Renovations began in 2016. The dome features a framework of intersecting glass and steel, manufactured by German-based firm Gartner. There’s no doubt the top floor will not only be drenched in natural light but also offer unique views of Union Square and beyond.

  • Latest New School Construction Update

    Next week (October 22 to October 26), Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on upper floors will continue. Curtain wall installation on the lower floors will proceed along 14th st. inside the construction site. The crane that is on site will remain for the duration of curtain wall installation and will not affect pedestrian or automotive traffic.

    The following week (October 29 to November 2) Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation will continue on all floors. Curtain wall installation on the lower floors will proceed along 14th st. inside the construction site.

    This weekend the site will be open on Saturday, October 20th for superstructure related activities and curtain wall installation between the work hours of 7AM and 5PM as permitted by the City. Con Ed will be working in the street.