  • Latest Construction Update: More of the Same

    From The New School:

    Next week (September 19 to September 23), Contractors will continue to excavate earth and rock, and load out material. Installation of bracing rakers and line drilling will progress as well. Concrete foundation walls around the perimeter of the site and slab on grade work will continue. Interior core foundation work and underground electrical and plumbing will proceed. Contractors will be removing the interior earth ramp. DOT approved street connections to underground utilities on Fifth Avenue will progress. A small cherry picker crane will arrive on site next week, and be stationed inside the Fifth Avenue fence. This crane will remain on site for approximately two months.

    The following week (September 26 to September 30 ), we will continue with concrete foundation walls and slabs, line drilling, rock excavation, loading out, interior core foundation work, street utility connections on Fifth Avenue, and underground electrical and plumbing.

    DEP continues to repair the water main along 13th Street. As part of this work, the DEP may periodically shut water service off. This work is out of our control.

    The site will be open on Saturday, September 17th. Work hours are between 9AM and 5PM as permitted by the City. To control noise levels, work activities will be limited to the placement of formwork, plumbing and electrical work, site utility connections, waterproofing and rebar for concrete placement, and the installation of walers and braces. There will be no rock excavation, rock chopping, or hauling on Saturday.

  • What’s Going On with the Burned-Out Building?

    Curbed reports: The curvy low-rise building at 61 Fifth Avenue, devastated by fire in 2006, has been marked for death ever since the structure—a former Scrafft’s luncheonette (see photo at top left circa 1940)—was sold to a developer in early 2008. An architect was quickly enlisted to draw up plans for a 10-story building with apartments and ground-floor retail, and it was made clear that the current 61 Fifth Avenue was too far gone to be preserved in any manner. Has the economy put a pause on those plans? Perhaps, but broker-blogger Andrew Fine reports that demolition permit was issued for the property in December, so the wrecking ball could come calling any day now.

  • Canadian Donuts Invade Union Sq.

    A news flash about the Zen Palate site on Union Sqare East, and it’s decidedly downmarket:

    “The Riese Organization just purchased 34 Union Square (between 15th and 16th), formerly home to Zen Palate and plans to install a TGI Friday’s and a bonus Tim Horton’s in the space. Its been vacant in the two years since Zen Palate vacated due to “astronomical and non-negotiable increases” in their rent, a rent that has dropped 40% in the last six months. Choice quote: “…while many chefs in the district purchase food from the popular green market there, T.G.I. Friday’s will not join them, says Mr. Riese. ‘We are not that type of restaurant…'” Indeed.

  • The Alleged New School Construction Schedule

    Here’s what they’re currently saying:

    “With demolition and abatement complete, Tishman Construction and the Durst Organization have moved on to the next major phases of the construction process: clearing and laying the foundation. Future deadlines include the following.”

    Present to August 2011: Excavation foundation

    September 2011 to May 2012: Superstructure erection

    May 2012 to October 2012: Façade and building enclosure