    We’ve had Thai restaurants as downstairs neighbors before, and now a new one may be coming to replace Corkbuzz at 13 East 13th. A liquor license application has been filed by Varith, a “family-run” Thai restaurant that has a highly regarded sister operation called Valla Table in Hell’s Kitchen run by Chuck Valla, who was a private chef prior to opening this first place in 2021. Looks good.

  • Latest New School Construction Update

    DOB has granted our request to start placing our concrete at 6am, which will allow us to finish this work earlier in the evening. We have 5 more instances like this until we finish our superstructure in early June.

    Therefore next week (April 23 to April 27), Superstructure work will continue at the 14th and 15th floor levels. Monday, April 23rd, and Thursday, April 26th, we will have a pour with a 6 am start time and similar end time, weather permitting. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    The following week (April 30 to May 4), we will continue superstructure concrete and slabs on the 15th and 16th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    This weekend the site will be open on Saturday, April 21st for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

    In addition to the normal work on the job site, we will have an additional crane on site at 13th st. and 5th ave. to install the stair trusses on the west side of the building. The crane will be completely on site and should not interfere with pedestrian or automotive traffic in the area.

  • Latest New School Construction Update

    Next week (February 11 to February 15), material and equipment deliveries and installation work will continue on all floors inside the building as well as roof work. Additionally we will begin work on the new sidewalks around the building.

    The following week (February 18 to February 22), Material and equipment deliveries and installation work will continue on all floors and roofs as well as sidewalk work. The site will be closed on Monday, February 18th, for the holiday.

    This weekend the site will be open on Saturday, February 9th for interior, superstructure and sidewalk related activities between the work hours of 7AM and 5PM as permitted by the City.