How annoying. The New School construction site seems to be getting its daily dumpster deliveries at 4:15AM. So noisy. Good morning!

Similar Posts

  • Latest New School Construction Update

    Next week (July 16 to July 20), Mechanical equipment deliveries and work on them will continue at the 17th and 18th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue. Curtain wall installation will continue.

    The following week (July 23 to July 27), we will be working on the machine room levels on the 17th and 18th floors. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    This weekend the site will be open on Saturday, July 14th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

  • Wait, Wait, Wait, the Busway Is NOT Back

    In a last-minute appeal, a judge on Friday hit the brakes on the city’s plan to ban private car traffic from a stretch of 14th Street, NY1 reports.

    A judge granted the appeal, which was filed in the state appellate court division, and halted the pilot program for the second time in two months. The decision forces the city’s Department of Transportation (DOT) to suspend its plans and likely move to appeal the sudden about face.

    The ruling comes just three days after a judge lifted a temporary restraining order on the program and as DOT crews prepared to launch the 18-month pilot program between Third and Ninth avenues on Monday. The stalled pilot aims to block private car through traffic from the busy road to speed up bus commutes during work on the L train’s Canarsie Tunnel. Pick-ups, drop-offs, and garage access would still be permitted under the plan.

    The busway was set to launch Monday at 6 a.m. It was originally planned for July 1.