  • Latest New School Construction Update

    Next week (January 9 to January 13), Superstructure work will continue at and 2nd , 3rd and 4th floor levels. The sidewalk shed along 14th Street has been opened and we will begin working on the side walk shed along 5th ave.

    The following week (January 16 to January 20), we will continue superstructure concrete and slabs on 2nd , 3rd and 4th floor levels. The weekend of Saturday 1/14/12 we will be installing a new crane that will service the site for the duration of the job.

    This weekend the site will be open on Saturday, January 7th, for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

  • Art!

    Last Friday, NYC Parks & Recreation, CYNTHIA-REEVES PROJECTS, and the Union Square Partnership officially cut the ribbon on LOTUS, the newest piece of temporary art in the Union Square Park Triangle. LOTUS was the creation of Seoul-based artist Jaehyo Lee. To create the piece, the artist meticulously carved, shaped, burned the individual wood elements attached to a steel armature that stretches 12 feet high. The artwork has certainly made an impression as passersby who can be seen at all times of day stopping to look and touch the new art in the triangle.

    img_6796

  • Lastest New School Construction Update

    Next week (November 14 to November 18), DOT approved street connections to underground utilities on Fifth Avenue and 13th street will continue. Superstructure work will continue at cellar, 1st, and 2nd floor levels. A street crane will be moved into position early on Wednesday the 11/16 on 13th street to place structural steel in the building and should be out by the end of the day, weather pending.

    The following week (November 21 to November 25), we will continue superstructure concrete and slabs. Street utility connection work will continue. Sidewalk sheds will continue being erected around the perimeter of the site. The project will be closed on Thanksgiving Day, 11/24, and open for work on 11/25.

    This weekend the site will be open on Saturday, November 12th for superstructure related activities between the work hours of 9AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork, plumbing and electrical work, rebar for concrete placement and use of the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.